試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(2)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(2)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

During the project plan presentation meeting with the stakeholders. An issue was discussed and a resolution was reached, and all interested parties were on board. Sometime after the meeting, the project manager receives an e-mail from one of the key stakeholders saying they have changed. Their mind about the agreed to solution and would like to ger the group back together to discuss new options.What conflict resolution techniques should the project manager try first?
A、Compromising
B、Forcing
C、Smoothing
D、Withdrawing